Designed to a BREEAM Excellent Standard and occupied by Price Waterhouse Cooper, The commercial office space was awarded RICS South West Commercial Project of the year.

 

Utilising an innovative design solution, the BEMS uses the cooling potential of the dock water in the adjacent harbour to provide the environmental control.

Ensuring the strict Environment Agency legislation associated with the Dockwater system are adhered to, the BEMS provides the buildings means of maintaining its sustainability and minimal carbon footprint.

Project Facts

  • Design Consultant - WSP Parsons Brinkerhoff
  • Main Contractor - Wates
  • Services Contractor - Interserve Engineering Services
  • Client - Salmon Harvester Properties
  • BEMS Project Value - £260,000
  • BEMS Solution - Siemens PX